The channel is about 25m long |
By about 13:30 the channel was finished. Uli and I had already bored a hole in the wall under Harting 8 so the pipes could go through the wall/foundation and up to where they are needed. We were relatively lucky that there was a hole in the foundation - else we would have been kept busy for much longer. We managed to get the pipes in with a lot of pulling and shoving - the heating pipe was extremely stiff and so it was hard to bend it around corners.
By about 17:00, Stefan had filled most of the channel back in again. The pipes are now covered with 1.3 metres of clay and gravel, so they should be fine in case of frost.
The silo walls are broken through |
The channel is 1.3m deep |
The digger was able to get right in next to the wall |
The channel had to go around the side of Harting 10 |
Daniel had a go driving |
...and managed not to knock the house |
Luckily there was a hole in the concrete - otherwise we'd still be hammering away at it |
Provisional rain capture |
Stefan filled in most of the channel once the pipe was in |
We had to leave about two metres for fitting the pipe through the wall |
The channel had to go around in a curve so as to hit the wall of Harting 10 at 90° |
At the bottom of the photo you can see the first intersection of the channel with the old silo wall |
This is where we have to bore through the wall |
The first intersection of the channel with the silo wall (looking south) |
The thick pipe is the heating pipe. The other one carries electric and network cables |
Awesome job at the piping! Looks like there weren’t any complications, aside from the 90 degree corner that is. It really looks neater when the electric and network cables are underground, plus it’s less prone to accidentally getting cut. On the flip side, repairs can be an awful affair when it happens. It’s also good that the two pipes are in the same area. Definitely saves time when trying to map out where the problem is.
ReplyDeleteDarryl @ Milani.ca